Highlights of some of the many successful Vi-Spec past projects

 
Projects
Pembina Duvernay 1 Shallow Cut Gas Plant - Fox Creek, AB

Pembina Duvernay 1 Shallow Cut Gas Plant - Fox Creek, AB

Client: Pembina Gas Services

Assignment:

Vi-Spec provided the Electrical and Instrumentation Quality Surveillance for all vendor packages as well as the Site Representative for field construction, commissioning and start-up. Project was completed on time and under budget.


Suncor 2009 Spring Shutdown in Plant 52 & 53

Suncor 2009 Spring Shutdown in Plant 52 & 53

Client: Edmonton Exchanger (Suncor Edmonton Refinery)

Assignment:

Vi-Spec provided six Quality Control inspectors and one document control personnel for the 2009 Spring Shutdown in Units 52 & 53. Installation of new pipe spools, control valves, PSV and vessel and furnace repairs.


Suncor Refinery Hydrogen Recovery Unit Plant 52

Suncor Refinery Hydrogen Recovery Unit Plant 52

Client: Edmonton Exchanger (Suncor Edmonton Refinery)

Assignment:

Vi-Spec provided two Quality Control inspectors for the Hydrogen Recovery Unit in Plant 53.Installation of new pipe spools, control valves, PSV and other in-line piping components. Revamp three PSA vessels and installation of Sundyne Tail Gas Compressor.


CNRL Horizon Project Phase 1 Extraction Plant Construction

CNRL Horizon Project Phase 1 Extraction Plant Construction

Client: AMEC Americas

Assignment:

AMEC provided the Engineering, Procurement & Construction Management on this project for CNRL. Vi-Spec provided two inspectors to supplement the Quality Assurance Teamat site during the construction phase in 2007 and 2008.


CNRL – Horizon Oil sands Plant Phase 2/3 Expansion

CNRL – Horizon Oil sands Plant Phase 2/3 Expansion

Client: SCI

Assignment:

Provide 4 consultants for commodity inspections at several vendors’ works on piping components, fittings,and valves.


Foster Creek, Christina Lake, and Narrows Lake Projects

Foster Creek, Christina Lake, and Narrows Lake Projects

Client: Cenovus Energy

Assignment:

Provide Quality Surveillance consultants at several vendors’ works to audit fabrication activities on equipment including pressure vessels, pressure piping, steam generators, module construction, and structural steel fabrication.


Edmonton Refinery – Spring 2014 Plant Turnaround

Edmonton Refinery – Spring 2014 Plant Turnaround

Client: Suncor Energy Inc.

Assignment:

Provide 5 consultants to assist the owner with Quality Assurance, Inspection and Contractor Surveillance on spring 2014 FCCU and Alkylation units turnaround project.


Dow Chemical Fort Saskatchewan – Spring 2012 Plant Turnaround

Dow Chemical Fort Saskatchewan – Spring 2012 Plant Turnaround

Client: IRIS NDT

Assignment:

Provide 3 consultants to assist the owner with In-Service static equipment inspections and inspection of pressure piping repairs and replacements.


ABSA QMS Certificate of Authorization Permit

ABSA QMS Certificate of Authorization Permit

Client: Robert B Somerville Company

Assignment:

Assist the client with obtaining an ABSA QMS Certificate of Authorization Permit to construct and repair B31.1 and B31.3 pressure piping. Vi-Spec continues to provide QC consultants to Somerville for their pressure piping construction projects.


Oakville Refinery (Suncor) – Fall 2013 Plant Turnaround

Oakville Refinery (Suncor) – Fall 2013 Plant Turnaround

Client: Team Inc.

Assignment:

Provide 4 consultants to assist the owner with In-Service static equipment inspections and pressure piping installations.


Horizon Oil sands Plant – 2013 Plant Turnaround

Horizon Oil sands Plant – 2013 Plant Turnaround

Client: CNRL

Assignment:

Provide 1 consultant to assist the owner with In-Service static equipment inspections and a 52” hot process water line tie in.


Horizon Oil sands Plant – Train 3 Hydrotransport and Ore Prep Plants

Horizon Oil sands Plant – Train 3 Hydrotransport and Ore Prep Plants

Client: CNRL

Assignment:

Provide 2 consultants to assist the owner with Pre-commissioning and Quality document turnover review.


Suncor 2009 Spring Shutdown in Plant 52 & 53

Suncor 2009 Spring Shutdown in Plant 52 & 53

Client: Edmonton Exchanger (Suncor Edmonton Refinery)

Assignment:

Vi-Spec provided six Quality Control inspectors and one document control personnel for the 2009 Spring Shutdown in Units 52 & 53. Installation of new pipe spools, control valves, PSV and vessel and furnace repairs.


Suncor Refinery Hydrogen Recovery Unit Plant 52

Suncor Refinery Hydrogen Recovery Unit Plant 52

Client: Edmonton Exchanger (Suncor Edmonton Refinery)

Assignment:

Vi-Spec provided two Quality Control inspectors for the Hydrogen Recovery Unit in Plant 53. Installation of new pipe spools, control valves, PSV and other in-line piping components. Revamp three PSA vessels and installation of Sundyne Tail Gas Compressor.


CNRL Horizon Upgrading Plants, Phase 1 and 2 construction

CNRL Horizon Upgrading Plants, Phase 1 and 2 construction

Client: Canadian Natural Resources Limited

Assignment:

Vi-Spec provided the Quality Surveillance at source for Upgrader pipe rack modules, coker vessels, reactor vessels and stripper absorber tower at the supplier's works. Suppliers were TIC, Kiewit, KBR and PCL for modules, Dacro and Hitachi (Saskatoon) for the vessels. On-site completion of reactor's fabrication.


CNRL Horizon Project Phase 1 Extraction Plant Construction

CNRL Horizon Project Phase 1 Extraction Plant Construction

Client: AMEC Americas

Assignment:

AMEC provided the Engineering, Procurement & Construction Management on this project for CNRL. Vi-Spec provided two inspectors to supplement the Quality Assurance Team at site during the construction phase in 2007 and 2008.